Plum Orchard

Update: August 1st, 2007

Sea Island Cotton

Update December 19th 2007

1st Tour Since Renovation

Plum Orchard Short History

Nearing the End Oct. 25, 2007

Update September 28th 2007

Update August 14th 2007

Update August 7th 2007

August Update

Overview of Plum Orchard

Plum Orchard Page 1

1st Story Floor West Side

1st Story Floor East Side

2nd Story Floor West Side

2nd Story Floor East Side

Attic

The Kohler Connection

Elevator

A/C -- 19th Century

Electrical Work

Outbuildings

Ventilation Work

Major systems are getting into their finishing phase. 

The fire sprinkler system with its 12,000-gallon surge water supply is almost complete.  On this date, they were getting ready to pour concrete around some joints in the delivery pipes.  This concrete will help the joints withstand the surge of pressure that would occur when the system activates.

While there are still lots of loose wires yet to be connected, the new, emergency generator should be put on its pad and wired next week.  Light fixtures that were removed at the beginning of the work are almost completely replaced.  New lines that have been laid throughout the mansion are mostly live.  The electronics for the fire sprinkler system are complete.  Grounding for the electronic systems is almost complete.

But, there are still some things that need to be done.

 

One of the columns and the railing on the piazza are rotten.  This is located between the House Keeper’s Office and the Storage Room on the South end of the house.  I don’t know what the Park Service will authorize, but the damage to the column and railing is pretty severe.

 
Moving around to the front of the house. You can see in the photograph that there was once two large palm trees in the front. The one on the South side died and then fell, damaging the eves and gutters.

 

Finally, the top step on the back piazza (the piazza that was completely replaced) is severely cracked and will be replaced.

 

However, even in the August heat, the front yard is still something amazing.

If you have any suggestions or corrections that need to be made to these pages, please let me know.

Copyright © 2011 SamLindsey.com.  All rights reserved.

Privacy Statement

Reproduction in whole or in part without permission is prohibited